Programme Overview (progress to date)

Almost one year into our two year programme – how are we doing?

Block 6 (Rede)

• Exterior envelope ongoing
• Internal fit-out continues – partitions commenced in core
• Roof and plantroom walls commenced


Block 5 (Pont)

• Structural floors completed
• Module installation completed


Block 4 (Irthing)

• Structural steel envelopes and floor completed
• Module installation commenced


Block 3 (Derwent)

• Substructure completed
• Steelwork and lift shafts commenced


Block 2 (Breamish)

• Substructure on going


Block 1 (Alwin)

• Substructure continues
• Marketing module substructure completed.

Sometimes a picture is better than words, but word on the blocks is that we are on target and are doing very well!

Park view student village overview

published on: 31 July 2017